Spencer Tuck Regional Park Design Study
The Peace River Regional District (PRRD) has started a design study to identify and plan for enhancements to safety, accessibility and overall appeal of Spencer Tuck Regional Park.
The study will examine challenges such as traffic flow, parking, washrooms and boat launch access. It will also evaluate whether the boat launch needs repairs or replacement. After completing the study, a plan will be developed to address the current and future needs of park visitors and other interest groups.
The PRRD is committed to cultural safety and meaningful collaboration with all local partners and interest groups throughout the planning process. Local First Nations Land Use Departments have been notified and invited to engage on the design study at Spencer Tuck Regional Park.
The public engagement phase for this project concluded on November 24, 2024. Please refer to the project timeline for more information.
The Peace River Regional District (PRRD) has started a design study to identify and plan for enhancements to safety, accessibility and overall appeal of Spencer Tuck Regional Park.
The study will examine challenges such as traffic flow, parking, washrooms and boat launch access. It will also evaluate whether the boat launch needs repairs or replacement. After completing the study, a plan will be developed to address the current and future needs of park visitors and other interest groups.
The PRRD is committed to cultural safety and meaningful collaboration with all local partners and interest groups throughout the planning process. Local First Nations Land Use Departments have been notified and invited to engage on the design study at Spencer Tuck Regional Park.
The public engagement phase for this project concluded on November 24, 2024. Please refer to the project timeline for more information.
-
Newsfeed
Share Newsfeed on Facebook Share Newsfeed on Twitter Share Newsfeed on Linkedin Email Newsfeed linkPublic Engagement Wrap-up
November 25, 2024
The Spencer Tuck Design Study public engagement has concluded. We received 38 responses to the community survey and had and had 11 attendees across the in-person and virtual open houses on November 16, November 19 and November 23, 2024.
Next Steps
Our team is now compiling your feedback into a draft study. The final design study report, including recommendations, will be presented to the Regional Board in March 2025.
Stay Updated
For important project updates, subscribe for updates on this project page under the 'Subscribe' tool.
Thank you to everyone who participated and contributed valuable feedback! We look forward to using your input to enhance the safety, accessibility and appeal of Spencer Tuck Regional Park.
Zoom Join Information, Virtual Open Houses
November 7, 2024
We're excited to invite all residents to our upcoming virtual open house for the Spencer Tuck Regional Park Design Study. If it's your first time, no worries—joining is simple! You can participate using your computer, tablet, cellphone, or even a landline. Here’s how:
By computer or cellphone
Join by clicking this link: https://us02web.zoom.us/j/87610086463?pwd=zAPfKGWmtJ6h1f5JAAUXRwtVxXxC5M.1
For more information about joining a Zoom meeting with your computer or handheld device, please review this help article.By landline (dialing-in)
Call +1 647-374-4685 and enter the following codes when asked:
Meeting ID: 876 1008 6463
Passcode: 165514For more information about joining a Zoom meeting by phone, please review this help article.
Upcoming Open Houses
November 5, 2024
We're hosting open houses! Join us in-person or virtually to discuss making Spencer Tuck Regional Park a welcoming place for everyone. No reservations are required and the events are open to everyone. If you have any questions about the open house events, please contact the Peace River Regional District at 250-784-3200.
In-Person Open House
November 16, 1pm-3pm: Moberly Lake Elementary School
Event link: https://www.facebook.com/events/1068419548076477/
Virtual Open HousesNovember 19, 6-8pm: Zoom
Join link: https://us02web.zoom.us/j/87610086463?pwd=zAPfKGWmtJ6h1f5JAAUXRwtVxXxC5M.1
Meeting ID: 876 1008 6463
Passcode: 165514November 23, 10am-12pm (Noon): Zoom
Join link: https://us02web.zoom.us/j/81453781950?pwd=B0aL4LtoCDiunnR5WaUuMpn40KaYYy.1
Meeting ID: 814 5378 1950
Passcode: 912282Public engagement open!
October 28, 2024
We are excited to announce that the Peace River Regional District (PRRD) is kicking off a design study for Spencer Tuck Regional Park! This study aims to identify enhancements to safety, accessibility and overall appeal at the park. As part of this effort, we'll also be looking at the park's boat launch to see whether the best course of action is repair or replacement. Once the study is done, we'll create a plan to meet the needs of park visitors and other interested groups.
What the Study Covers
We’re looking at:
- Traffic flow
- Parking
- Washrooms
-
Boat launch access
How to Participate
We want to hear from you! Share your feedback in the following ways:
- Online Survey: Share your thoughts with us.
- In-Person Open House: Drop by Moberly Lake Elementary School (6531 Lakeshore Drive) on November 16 from 1pm to 3pm.
-
Virtual Open House: Join us online on November 19 at 6pm or November 23 at 10am. Details on registration will be provided soon.
Our Commitment
The PRRD is dedicated to working together with local partners, park neighbours and interest groups, including First Nations, to ensure a collaborative and inclusive planning process.
-
About the park
Share About the park on Facebook Share About the park on Twitter Share About the park on Linkedin Email About the park linkSpencer Tuck Regional Park is a charming 5.18-hectare spot on the north side of Moberly Lake, about 32 km north of Chetwynd. The lake itself stretches 14 km with a 41 km shoreline. This day-use park offers five (5) fire pits and picnic tables, an outhouse, short walking trails and the only public boat launch on the lake's north side. It's especially popular in summer.
The park is bordered by private properties, with a transportation right of way running through it. Since 2023, the park has been closed during winter months.
-
FAQs
Share FAQs on Facebook Share FAQs on Twitter Share FAQs on Linkedin Email FAQs linkWhere is Spencer Tuck Regional Park?
Spencer Tuck Regional Park is a 5.18-hectare property owned by the Peace River Regional District (PRRD), situated on the north side of Moberly Lake, about 32 km north of Chetwynd. Moberly Lake spans about 14 km and has a shoreline of roughly 41 km.
View the park map.
What are the goals of the project?
The PRRD is creating a design study to improve Spencer Tuck Regional Park. This will examine challenges such as traffic flow, parking, washrooms and boat launch access. It will also evaluate whether the boat launch needs repairs or replacement. After completing the study, a plan will be developed to address the current and future needs of park visitors and other interest groups.
Whose input will be considered and how can I provide input?
We're seeking feedback from the public, community groups and park neighbours to make sure our design study and proposed improvements meet everyone's needs.
Here's how you can participate:
• Take our online survey
• Come to our in-person open house on November 19 at Moberly Lake Elementary from 1pm to 3pm
• Join one of our two virtual open house events on November 19 and 23 (more information under Key Dates)
We'll also be talking to park interest groups to gather their thoughts.
Who's Listening
-
BC
Phone 250-784-3200 Email bryna.casey@prrd.bc.ca -
JB
Phone 250-784-3200 Email jennifer.bell@prrd.bc.ca -
IS
Email ISmith@elac.ca
Project Timeline
-
Phase 1: Project Launch (September 2024)
Spencer Tuck Regional Park Design Study has finished this stage -
Phase 2: Site Visit (October 2024)
Spencer Tuck Regional Park Design Study has finished this stage -
Phase 3: Staff & Public Engagement (Late October-November 2024)
Spencer Tuck Regional Park Design Study is currently at this stage -
Phase 4: Design Study Draft (January-February 2025)
this is an upcoming stage for Spencer Tuck Regional Park Design Study -
Phase 5: Final Design Study Report & Board Presentation (March 2025)
this is an upcoming stage for Spencer Tuck Regional Park Design Study
Key Dates
-
November 16 2024
-
November 19 2024
-
November 23 2024